East Coast Main Line: Tunnel painstakingly pushed underground

Date:

A concrete box weighing more than the Eiffel Tower has been pushed under a railway line to form a new tunnel, in a “UK first” for engineering.

The 11,000-tonne, 155m (510ft) structure was moved into place under the East Coast Main Line at Werrington, Peterborough, at 150cm (60in) per hour over nine days.

The tunnel, opening at the end of 2021, will separate freight and passenger trains on the London to Edinburgh route. It will lead to faster and more reliable services, said Network Rail.

The project is part of £1.2bn being spent to upgrade the line.

Share post:

Subscribe

Popular

More like this
Related

Celine Dion announces comeback concerts September-October in Paris

Céline Dion is officially coming back to the...

Save up to 52% on Samsonite, Anker and more for summer vacations

I live (and work!) to travel. Whether that means...

Tech Life – Recommending: 13 Minutes Presents Artemis II

Available for 29 daysHumans are returning to the Moon...

What is the Superintendent of Public Instruction responsible for?

What is the Superintendent of Public Instruction responsible for?...